Skip to main content

CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS!

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Hazard assessment is critical during the design, fabrication, and installation of system modifications to ensure hazards and potential hazards are addressed prior to system start-up and operation.

All chemicals, including gases, should be clearly labeled and expiration dates (if applicable) identified. Incidents are more common when incompatible chemicals are mixed or when chemicals are stored/transferred using incompatible equipment.…

Diligence needs to be practiced when performing assigned work tasks. To guard against complacency, it is necessary to emphasize adherence to established procedures, including appropriate reviews of preventive maintenance instructions (PMI) and…

The lessons learned in this situation center around basic conduct of operations principles. Policies and procedures related to operations performance, safety performance, and management oversight were in place. They were not employed…

On-site personnel performing treatment of reactive metals/chemicals must continue to exercise caution. Although there is an inherent risk in treating reactive metals/chemicals, personnel must adhere to conduct of operations principles to include…

Thoroughly plan and schedule work such that the correct tools are at the job site. If activities take place that take the job supervisor away from the job location while critical steps are to be performed, the work should be temporarily stopped.…

A flammable gas explosion is an analyzed hazard and gas detection/shut off is a safety significant control system that requires a limiting condition for operation (LCO). The rigor of the evaluation of flammable gas systems was inadequate. There…

In addition to the probable causes listed above, the lack of a standard operating procedure for hydrogen leak detection was one of the probable causes of this incident. Additional contributing factors included the following:
- Severe pipe…

The company investigation revealed that the incident arose because insufficient water was added to the batch. This resulted in a rapid increase in temperature and evolution of hydrogen gas following the addition of aluminum powder in the last…

The following actions were proposed as a result of this incident:

  •  The company in charge of valve calibration and maintenance will be subject to approval of the plant service inspection team.
  •  Plant operating…

Implement rigorous assembly, verification, and documentation procedures for equipment.

Increase automated leak detection frequency.

Do not interconnect hydrogen drain trap lines with other drain lines

Thoroughly inspect equipment installation to manufacturer’s installation instructions

Warn against unauthorized field modifications

Consult the…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts